docs: migrate repository guidance to Gitea
This commit is contained in:
1 parent
0d900fd72d
commit
7d60157863
31 files changed
+180
-102
No files matched your search
@@ -7,9 +7,9 @@ the benchmark fixtures. The latest full functional coverage run passes 652 tests
|
||||
across 34 files under the 2 GB Node heap limit, excluding the separate benchmark.
|
||||
This does not establish a passing performance protocol.
|
||||
|
||||
MR pipeline 320 passed all 652 functional tests in 109.43 seconds, then the
|
||||
seven-scenario protocol timed out at its unchanged 300-second limit without an
|
||||
out-of-memory failure. In an earlier diagnostic run, the loaded-year warm-up took
|
||||
Before the Gitea migration, GitLab pipeline 320 passed all 652 functional tests
|
||||
in 109.43 seconds, then the seven-scenario protocol timed out at its unchanged
|
||||
300-second limit without an out-of-memory failure. In an earlier diagnostic run, the loaded-year warm-up took
|
||||
184.36 seconds and its first measured repetition began about 251.78 seconds into
|
||||
the protocol. Those diagnostic timings precede the final period-projection cache
|
||||
and the planned original-decision-trace removal, and are not a result for either.
|
||||
@@ -19,12 +19,15 @@ verification. #78 owns benchmark verification and implementation of further
|
||||
optimizations when needed, after #76 removes tracing and #77 verifies the retained
|
||||
behavior. All seven scenarios, one warm-up and two measured repetitions per
|
||||
scenario, the 2 GB heap limit and the 300-second timeout remain required for #78.
|
||||
At the user's request, CI runs the benchmark in a separate job with
|
||||
`allow_failure: true` while #78 is open. Functional coverage tests and all other
|
||||
required checks remain blocking. #78 must restore the required benchmark gate
|
||||
At the user's request, the preserved CI configuration defines the benchmark in a
|
||||
separate job with `allow_failure: true` while #78 is open. Functional coverage
|
||||
tests and all other required checks remain blocking. #78 must restore the required benchmark gate
|
||||
after the unchanged protocol passes. A green pipeline during this exception
|
||||
does not establish a passing benchmark. No automatic elapsed-time planning
|
||||
cutoff is introduced.
|
||||
cutoff is introduced. CI execution is frozen and Gitea Actions is disabled pending
|
||||
[issue #268](https://gitea.nessar.fr/nessar/vac-optimizer/issues/268); the separate
|
||||
advisory benchmark job must be carried into the converted workflow. See the
|
||||
[CI migration status](../../README.md#continuous-integration).
|
||||
|
||||
The results below document earlier implementations and protocols. They are
|
||||
historical measurements rather than the performance result for composable rules.
|
||||
|
||||